    Retrospective Application of BS7671 (Wiring Regulations) ?

    I have a tenanted flat in Scotland. The property is about 20 years old and part of a fairly large development. The wiring passed the EICR at its last application 5 years ago, but has recently been given a fail because the consumer unit doesn't meet the latest version of BS7671 (18th Edition) (Condition of enclosure in terms of IP and fire ratings - C2). I understand that the new Edition of BS7671 has come into force since the previous inspection, but find it hard to believe that retrospective action to replace the consumer unit with one to the latest spec is (at a not inconsiderable cost) needed to gain an EICR pass this time around. Should I challenge the inspection result ? Any comments welcome...

    #2
    It depends on the person carrying out the inspection - because they are correct that the unit is not to the current specification, but they exercise their judgement in noting the severity of the issue.
    Many electricians would record that as a C3 issue, which is non-compliant but a possible improvement rather than something requiring a correction.

    My own would normally do that, but, on one occassion pointed out that the other work they would need to do made it a simple (and cheaper) job if done at the same time and in another case that the unit wasn't just non-compliant it was, in their view, badly installed and that they wanted to change it.

    Note that I'm not in Scotland, so it's possible the rules are different.
    When I post, I am expressing an opinion - feel free to disagree, I have been wrong before.
    Please don't act on my suggestions without checking with a grown-up (ideally some kind of expert).

    Comment


      #3
      Thanks jpkeates, I share your view and fear that I'm being taken for bit of a ride for a lot of expensive work that isn't strictly necessary. The unit was installed iaw the standards in place at the time, is in good condition and has not been modified since installation. There are no other problems with the system. I agree that a C3 would be more appropriate, but I'm not sure if that's negotiable now.

      Comment


        #4
        I recommend you google electrical safety council best practice guide number 4 , issue 5

        a plastic fuseboard can only be coded as a C3

        if they disagree with you, ask them for the regulation number to back up their coding

        FYIW I am totally fed up with the I d I o t s that write such awful regulations

        Comment


          #5
          I tested a flat today and it failed due to IP issues (as well as a host of other stuff)

          In simple terms any hole on the top of a consumer unit should not allow a 1mm wire to get in and other parts are different.
          See the YouTube video below

          The good news is that the IP problem can go away by filling holes with silicone sealant (not allowing it to go inside the unit over things obviously)

          As far as the unit being plastic - this is a C3 (does not meet current standards but meets previous ones), this assumes things inside are OK and there is no evidence of burning etc.

          Comment


            #6
            Thanks for your comments / advice - I will certainly be challenging the report, with a bit more confidence now.

            Comment

            Latest Activity

            Collapse

            • Reply to PAT Failure - Gas hob
              by nukecad
              In general -

              If it is plugged into a socket then it comes under PAT.
              If it is hard wired in then it comes under EICR.

              Think of a free standing electric cooker.
              Lower powered ones, under 3kW, that have a plug are not part of the electrical installation, they don't...
              13-08-2022, 09:35 AM
            • PAT Failure - Gas hob
              by MikeGreene
              My agents have recently taken over carrying out PAT Tests for my properties - it is a Selective Licence scheme area, and PAT Tests are a requirement.
              They have already found (unsurprisingly, given how many gunk up etc) two properties where the ignition button is not working and have failed the...
              11-08-2022, 12:48 PM
            • Reply to PAT Failure - Gas hob
              by Firebug
              It's not PAT it's the in service inspection and testing of electrical equipment and fixed equipment does come under it. The hobs would fail the functional test aspect of the procedure....
              12-08-2022, 20:56 PM
            • Reply to PAT Failure - Gas hob
              by royw
              I wouldn't expect a gas hob to need a PAT test either, it's a fixed item not a portable one. As long as it's passed the GSC I think that's all you need.
              12-08-2022, 15:07 PM
            • Elements of a proper gas safety check
              by AndrewDod
              Any gas competent people out there who can confirm exactly what a gas engineer should be doing as part of a boiler service and gas safety certificate.

              Just had an incident where a (smallish) gas leak in a wall was found a few weeks after such a service. It was discovered by the energy...
              18-07-2022, 11:43 AM
            • Reply to Elements of a proper gas safety check
              by gnvqsos
              ash72,

              They should do a flue analysis to ensure the gas is fully combusted ,and measure efficiency of the boiler..
              12-08-2022, 14:47 PM
            • Reply to Elements of a proper gas safety check
              by gnvqsos
              A tightness test at the meter should precede any work on gas pipes and devices.. If no leaks before the work commences, any subsequent leak is attributable to that fitter .I would guess that meter installers are not trained to a hih standard and have not learnt first principles, as a Gas sake engineer...
              12-08-2022, 14:45 PM
            • Reply to Asbestos Survey Report
              by Perce
              Thank you All.

              NSUK have now done an independent survey of the common parts for me very quickly.

              The management company is now also doing the survey but I did not want to wait for their report.

              I have asked the surveyor if it was a legal requirement...
              12-08-2022, 11:33 AM
            • Asbestos Survey Report
              by Perce
              Hello

              I am selling a flat in a residential block of flats. My buyer's solicitor has requested an asbestos report saying the building was built before 2000 so it is a legal requirement to have it.

              The building was built in 1998 and the Management Company did not do it. ...
              10-08-2022, 14:44 PM
            • Reply to PAT Failure - Gas hob
              by nukecad
              If you do disconnect it then I'd remove the igniter button from the hole and replace it with a plastic blanking plug.

              That way it's obvious that there is no igniter and not simply a broken one.
              12-08-2022, 11:10 AM