Licence to alter

Collapse
X
  • Filter
  • Time
  • Show
Clear All
new posts

  • Affinity
    started a topic Licence to alter

    Licence to alter

    Hello,

    I would like your view.
    In a licence to alter, is the following timeline pretty standard?
    - for the works must be started within six months from completion of the licence
    - to be completed within 12 months from completion of the licence

    12 months seem a long time. What is your view.

    Thank you in advance

  • flyingfreehold
    replied
    the key thing is that the usual buildings insurer will not cover the works in progress and the contractor must have cover for work in progress

    Leave a comment:


  • Affinity
    replied
    Much appreciated. Thank you, Lawcruncher

    Leave a comment:


  • Lawcruncher
    replied
    Definitely not. The time limit is not too long for a conversion. It allows for all the sort of delays that can occur. If I were acting for a leaseholder I would go for belt and braces and be looking for a bit longer. In fact I am not sure a time limit is really needed. More important is to provide that once the works are started they are proceeded with diligently.

    Leave a comment:


  • Affinity
    replied
    Thank you, Lawcruncher.
    Do you consider converting the loft into a second bedroom and bathroom something minor?

    Your view is appreciated. Many thanks

    Leave a comment:


  • Lawcruncher
    replied
    Depends on the nature of the works, but I would not say it is too long for anything other than something very minor.

    Leave a comment: